FINALTERM  EXAMINATION
Spring 2010
CS605 Software Engineering-II
Question No: 1    ( Marks: 1 )    - Please choose one
 A law affirming that to continue after a certain level of performance has been reached will result in a decline in effectiveness. This law is know as __________________

       ► Law of Diminishing returns

       ► Law of effectiveness

       ► Law of Saturation

       ► Law of Marketing returns

   
Question No: 2    ( Marks: 1 )    - Please choose one
 Build and Fix model is a ___________ type of software development activity.

       ► Mathematical
       ► Perfect
       ► Haphazard
       ► Planned
   
Question No: 3    ( Marks: 1 )    - Please choose one
  In _________________ a team is structured along a traditional hierarchy of authority
       ► closed paradigm
       ► synchronous paradigm
       ► random paradigm
       ► open paradigm
 
Question No: 4    ( Marks: 1 )    - Please choose one
 MTTC is the abbreviation of





       measured time to change
       mean time to collaborate
       mean time to change
       measure time to cope
   
Question No: 5    ( Marks: 1 )    - Please choose one
 While creating matrix for a set of projects, data should be collected that belongs to a similar domain
       ► true     
       ► false

Question No: 6    ( Marks: 1 )    - Please choose one
 The rapid application development model is

       Another name for component-based development.

       A useful approach when a customer cannot define requirements clearly
       A high speed adaptation of the linear sequential model.

       All of the given

   
Question No: 7    ( Marks: 1 )    - Please choose one
 While managing the historical data, we should consider the following except




       Data should be collected only from scientific projects and applications


       Data should be collected from many projects
       Data should be consistent
       Correct data should be taken
   
Question No: 8    ( Marks: 1 )    - Please choose one
 Quality costs may be divided into costs associated with

       prevention, appraisal, and failure
       people, process, and product
       customers, developers, and maintenance
       all of the given

Question No: 9    ( Marks: 1 )    - Please choose one
 When a software is delivered to a client and then client reports the bug in it then that bug is termed as

       Error


       Defect


       Mistake
       Fault

Question No: 10    ( Marks: 1 )    - Please choose one
 Mean Time To Repair (MTTR) is the

       Time when system remained unable for usage

       Time taken to fix the error

       Time taken to repair the software

       All of the given options are correct.

   
Question No: 11    ( Marks: 1 )    - Please choose one
 Reliability and Safety are same concepts with respect to software quality

       ► True
       ► False

Question No: 12    ( Marks: 1 )    - Please choose one
 Software configuration management is used to

       Manage change in the software

       Mange the financials accounts in an organization

       Manage the administration of company

       All of the given

   
Question No: 13    ( Marks: 1 )    - Please choose one
 SCM is the requirement of the ________ level(s) of CMM

       First

       Second and later

       Third and later

       Only Second

   
Question No: 14    ( Marks: 1 )    - Please choose one
 If a new version of a product is released by fixing the bugs in the previous release then it is termed as _________________
       Product Update

       Product Upgrade

       Defect Removal


       Product Performance

Question No: 15    ( Marks: 1 )    - Please choose one
 The Evolution Graph signifies the

       version relationship

       baseline of a particular release

       change control activity

       all of the given

   
Question No: 16    ( Marks: 1 )    - Please choose one
 The management of creeping requirements is important for the ease of

       maintenance

       development

       testing

       all of the given


Question No: 17    ( Marks: 1 )    - Please choose one
 Following are the components of a Legacy system except:

       business processes

       system hardware

       marketing

       application software


Question No: 18    ( Marks: 1 )    - Please choose one
 There are many reasons for which the legacy system become difficult to maintain EXCEPT


       Language in which system was developed become obsolete

       lack of consistency as different parts of the system have been developed by different teams
       None of these

       No documentation is available


Question No: 19    ( Marks: 1 )    - Please choose one
 The application software is assessed on the basis of following factors except

       Documentation

       Understandability

       Code Refactoring

       Test data

   
Question No: 20    ( Marks: 1 )    - Please choose one
 The process of rediscovering the software design is called


       Reverse Engineering

       Business Engineering

       Business Process Engineering

       Forward Engineering

   
Question No: 21    ( Marks: 1 )    - Please choose one
 In ______________, new user and technology requirement can also be integrated into the re-engineering effort.


       Backward re-engineering

       Forward re-engineering

       Business Engineering

       Business Process Engineering

   
Question No: 22    ( Marks: 1 )    - Please choose one
 A redesigned business process must be prototyped before it is fully integrated into the business.

       False

       True



Question No: 23    ( Marks: 1 )    - Please choose one
 In ___________ representation of CMMI model, consideration is given to improve selected processes areas.

       Staged
       Continuous
   
Question No: 24    ( Marks: 1 )    - Please choose one
 The purpose of earned value analysis is to

       determine how to compensate developers based on their productivity

       provide a quantitative means of assessing software project progress

       provide a qualitative means of assessing software project progress

       set the price point for a software product based on development effort

   
Question No: 25    ( Marks: 1 )    - Please choose one
 The software plan is not a static document, it is frequently adjusted to make the project appear on track to meet all deadlines and quality targets.
       ► True
       ► False

Question No: 26    ( Marks: 1 )    - Please choose one
 There are tools available in the market for project tracking. These tools can autmomatically track and manage the project replacing the need of any human being as a Project Manager.
       ► True
       ► False
   
Question No: 27    ( Marks: 1 )    - Please choose one
 Timeline chart is also known as the _____________ chart
       Gantt
       PERT
       FREE LANCE
       None of the given

Question No: 28    ( Marks: 1 )    - Please choose one
 The processes at ----------- is focus on continually improving process performance through both incremental and innovative technological changes/improvements.



       Level 5
       Level 1
       Level 4
       Level 3

Question No: 29    ( Marks: 1 )    - Please choose one
 In a complex system that will lead to much ………..code to write and maintain.

       More
       None of the given
       Less
       Meaningless
   
Question No: 30    ( Marks: 1 )    - Please choose one
 Review is a type of _________ that helps preventing the bugs to move in the next stage of software development

       Bug seeding tool
       Filter
       Alarm
       None of the given
   
Question No: 31    ( Marks: 2 )
 Why software engineers collect measures?
To have the accurate requirments
To achive Goals more effectly and more effeciently
   
Question No: 32    ( Marks: 2 )
 Give two importances of reviews?
With Technical review you may come to know more about the technical requirments and specifications.
reviews the process description for compliance with the organizational policies, internal software standards, externally imposed standards, and other parts of the software project plan.
  
Question No: 33    ( Marks: 2 )
 Discuss the role of program restructuring in software reengineering?

In this case we modify source code and data in order to make it amenable to future changes. This includes code as well as data restructuring. Code restructuring requires redesign with same function with higher quality than original program and data restructuring involves restructuring the database or the database schema. It may also involve code restructuring.All will be insoftware reengineering/ Program is restructured after the reverse engineering phase.

   
Question No: 34    ( Marks: 2 )
 Give the properties of Capability Levels?

0  Incomplete
1  Performed
2  Managed
3  Defined
4  Quantitatively Managed
5  Optimizing


   
Question No: 35    ( Marks: 3 )
 What would this model depict?

Yes it will

Question No: 36    ( Marks: 3 )
 Give any six attribute of Requirements?

Software Quality Assurance
Quality Assurance
Cost of quality
SQA Activities
SQA Group Activities
Quality Control
   
Question No: 37    ( Marks: 3 )
 List the factors involved in calculating the cost of Reengineering?
Current annual maintenance cost for an application
Current annual operation cost for an application
Current annual business value of an application
Predicted annual maintenance cost after reengineering
Predicted annual operations cost after reengineering
Predicted annual business value cost after reengineering
Eestimated reengineering cost
Estimated reengineering calendar time
Reengineering risk factor
Expected life of the system


Question No: 38    ( Marks: 3 )
 How do you identify the problems in a software?
   


Question No: 39    ( Marks: 5 )
 Draw the Software Reengineering Process Model.




Question No: 40    ( Marks: 5 )
 Can you think it is difficult to implement CMM level in small software companies?

The CMM Level where basic project management processes are established to track cost, schedule, and functionality. That is, it is characterized by basic project management practices. It also implies that without project management not much can be achieved. In Small software house

        Project size
As the project size increases, the complexity of the problem also increases and therefore its management also becomes more difficult.

        Delivery deadline
Delivery deadline directly influences the resources and quality.

        Budgets and costs
A good estimate of budget, cost and schedule is essential for any successful project.

        Application domain
Application domain also plays an important role in the success of a project. The chances of success of a project in a well-known application domain would be much better than of a project in a relatively unknown domain.

So implementation of all the procedure for this Level can be a bit difficult for small software houses because they usually work on small projects where cost and time always metter.